Artemis I launch updates: Saturday launch scrubbed after reoccurring liquid hydrogen leak

It comes after the launch was scrubbed Monday due to an engine problem.

NASA kicked off Monday its plan to send an unmanned space capsule into the moon’s orbit, marking the initial launch in an ambitious plan to establish a long term presence on the moon for scientific discovery and economic development.

The space capsule, called Artemis I, will travel for roughly 40 days -- reaching as close as 60 miles from the moon, and then 40,000 miles above the moon when orbiting over its dark side -- before landing in the Pacific Ocean off the coast of San Diego.

After the launch was scrubbed, the next attempt will occur Sept. 3.


Next Artemis I launch attempt likely pushed to late September

A launch attempt on Monday or Tuesday is off the table following Saturday's large leak, NASA officials said.

NASA engineers will look at the rocket and determine if a launch window on Sept. 26 or Sept. 27 is a possibility, officials said during a Saturday press briefing.

The SpaceX launch on Oct. 5 that will send astronauts to the International Space Station will factor into the decision-making as well.

-ABC News' Gio Benitez


NASA to provide an update on Artemis I launch

Mission management team will meet Saturday to see if there is still a possibility for a launch, or if they will have to roll back into the vehicle assembly building, NASA Administrator Bill Nelson said speaking on NASA TV.

If they decide to roll back into the vehicle assembly building, then it will be an October launch, more likely toward the middle of October.

Nelson said the launch will happen when it is ready, saying, "This is part of our space program; be ready for the scrubs."


Saturday's launch scrubbed

The launch director has officially decided to scrub the launch scheduled for Saturday afternoon after NASA engineers detected several liquid hydrogen leaks.

NASA engineers encountered the leak while loading the propellant into the core stage of the Space Launch System rocket.

Multiple troubleshooting efforts to address the area of the leak did not fix the issue. NASA said engineers are continuing to gather additional data.

NASA has not yet said when it plans to make another launch attempt.

-ABC News' Gio Benitez



Liquid hydrogen leak detected for the 4th time

NASA engineers have detected a liquid hydrogen leak for the fourth time, despite three attempts to troubleshoot the leak. NASA said its teams are now discussing next steps.

A third leak occurred earlier in a cavity between the ground and flight side plates of a quick disconnect in the engine section. They attempted to warm up the quick disconnect to try to reset the seal then began flowing liquid hydrogen to the core stage.

NASA said the liquid oxygen tank of the core stage is full and is being replenished as some of the super-cooled propellant boils off.


NASA moves Artemis launch date to Saturday

NASA officials announced Tuesday that they've moved the launch of Artemis I to Saturday.

Mike Sarafin, Artemis mission manager, told reporters during a media briefing that the mission management team met earlier in the day and agreed on the new date.

"We agreed on what was called option one, which was to operationally change the loading procedure and start our engine chill down earlier," he said.

One of the reasons for the scrub on Monday was because engine three did not cool down enough to the point needed for ignition, he explained yesterday.

"We also agreed to do some work at the pad to address the leak that we saw and we also agreed to move our launch date to Saturday, September the 3rd," Sarafin added. "We are going to reconvene the mission management team on Thursday, September the 1st, to review our flight rationale and our overall readiness."